Nilkanth Steels plans expansion programme

Nilkanth Steels is planning to expand its manufacturing facility in Vadala in Mundra Taluk in Kutch district of Gujarat. The project involves expanding sponge iron production capacity from 72000 tpa to 144,000 tpa, rolling mill unit from 180,000 tpa to 360,000 tpa, addition of captive power plant of 2 MW and increasing waste heat recovery plant capacity by 4 MW.

Land required for the project is available.

Nilkanth Steel Project
Sr.
No.
ProductExisting
Capacity
(Ton/Annum)
Total Capacity
after Proposed
Expansion
(Ton/Annum)
1Sponge
Iron/Sponge
Pellets (Kiln)
72,000 (2
Kiln: 100
MT/Day each)
1,44,000 (4 Kiln:
100 MT/Day
each)
2Mild Steel, Ingots,
Billets, MS Rolled
Products, TM
Bars,
Channel/Angle
1,80,000 (2
Furnace:
Rolling Mill)
3,60,000 (4
Furnace: Rolling
& Section Mill)
3Captive Power
Plant
4 MW6 MW
4Waste heat
recovery boiler

Power
Plant

6 MW10 MW
Grand Total2,52,000 & 10
MW
5,04,000 & 16
MW

 

The project cost is estimated at ₹ 600 million. The project is expected to go operational by end 2020