Ankur Udyog Ltd is planning to set up a steel plant in Sahjanwa/Domharmafi villages in Gorakpur district of Uttar Pradesh. The project involves setting up of sponge iron unit (DRI) with a production capacity of 2,31,000 tpa, induction furnace (2,47,500 tpa), rolling mill unit etc., Land required for the project is around 79 acres which is already available.
It also involves setting up of 1 x 3 strand billet caster, captive power generation unit of 50 MW (24 MW -Waste Heat Recovery Boiler /26 MW FBC). The project cost is estimated at ₹ 33, 000 million.
The steel unit will produce TMT bars through hot charging route. As of January 2019, the project is in planning stage.
Project Location | Sahjanwa, Gorakhpur District,Uttar Pradesh |
Project Cost (in million) | ₹2,750 |
Project Capacity | 33000 tpa |
Project Status | Planning |
Commissioning Date |
Company Profile : Ankur Udyog Ltd