BMA Stainless is planning to expand its billet unit at Kalyaneshwari in Burdwan district of West Bengal. The project involves expanding MS Billet unit capacity from 120,000 tpa to 207360 tpa by installing additional 4 x 12 tons induction furnace units.
The project also involves modernizing the rolling mill capacity to add 87,360 tpa new capacity. No additional land is required for the project. The project cost is estimated at Rs. 80 million.
Project Location | Kalyaneswari, Burdwan district,West Bengal |
Project Cost (in million) | ₹80 |
Project Capacity | 870000 tpa |
Project Status | Planning |
Commissioning Date |